FEASIBILITY STUDY FOR HOTEL DEVELOPMENT AT SOUTH EAST COMMERCIAL PARK, NAIROBI CBD

Posted: May 04, 2010 | Views: 696 |

Project: Hotel Development in Kenya, Nairobi-CBD-South East Commercial Park.

Client: Mr. J M

Location: Nairobi CBD South East Commercial Park.

APRIL 2010

EXECUTIVE SUMMARY

This is a project proposal for the construction of a middle class Hotel on a parcel of land situated at Nairobi CBD South East Commercial Park.

The project has been conceived, designed and will be implemented by www.a4architect.com for Mr. J. M

The estimated development cost for the project is KES 355,500,000[USD 4,443,750].

The project completion period shall take 12 months from ground breaking to hand over.

Return on Investment shall be in a period of 1 year.

Total gross anticipated income per annum including food and beverage sales =388,800,000.00[4,860,000.00]

WWW.A4ARCHITECT.COM

A4architect is a dynamic property consulting company specializing in providing a one-stop service for the management and development of a variety of property development projects. It provides its clients, who may be property owners, developers or tenants, with the expertise to guide a project through the complex development process from concept through to building completion.

Depending on the requirements of their client, A4architect can provide a full or partial consulting service. The company's involvement can vary from sourcing suitable sites, arranging local authority approvals, managing the professional team or providing a complete project management service.

The principals behind the firm have several years experience in designing and managing to completion several projects of various natures as part of design and implementation teams for leading Project Management firms in Kenya as well as the Government of the Republic of Kenya.

THE PROJECT

The project comprises the construction of residential units for at South East Commercial Park, Nairobi on a subdivision measuring just about 0.25 acres.

The overall theme of the development would be one of maximizing on the plot use whilst maintaining reasonable individual privacy for occupants. The selection of the type and size of units to be erected as well as their layout has been done with the foregoing being foremost -A scenario where the property is developed to target the middle income bracket.

PHASED CONSTRUCTION

In order to ease the impact of the overall cost of the development it is proposed to carry out the construction in phases to be jointly agreed on with the client. The project can be phased in terms of vertical floor levels per floor as agreed with the client.

In order to enable planning of major infrastructural requirements such as water storage and soil water disposal right from the outset, a master plan of the entire development shall be evolved. Thus the capacity of some of the facilities may initially exceed the needs of the accommodation provided, but this would be done with the full knowledge that the development will grow to fully utilize the facilities provided.

Auxiliary features would include paved driveways and parking, extra water storage and planted landscaped gardens. The country ambience would further be enhanced by having strategically planted trees which would serve the added role of acting as wind breaks.

DEVELOPMENT BUDGET

The development budget is as follows:

80 No. self-contained accommodation rooms per floor for 5 No. Floors=400 No. Accommodation rooms.

Cost of construction per room fully furnished=KES 40,000 per square meter.

Area for each unit =16m2.

Total cost of construction for 400units = KES 256,000,000[USD 3,200,000]

Cost of construction for Restaurant, Kitchen, Laundry and Offices=

Restaurant-60m2

Kitchen=30m2

Offices-20m2

Laundry-20m2

Store-30m2

Total =160m2.

Total estimated cost of construction = KES 355,500,000[USD 4,443,750]

1.00 Building details

1.10 Type of unit :middle class hotel units.

1.11 Number of floors :5

1.12 Number of units in each floor :40

1.13 Gross floor area per Unit m2: 16

1.14 Building Cost per m2-fully furnished :40,000

1.15 Building cost per unit :KES 640,000 [USD 8,000]

1.16 Overall building cost : KES 260,000,000[USD 3,250,000]

2.00 Construction cost

2.10 Preliminaries      6,500,000.00   [USD 81,250]          2.5% of item 1.16

2.11 Building works  KES 260,000,000[USD 3,250,000]

2.12 Infrastructure      39,000,000.00  [USD 487,500]          15.00% of item 1.16

2.13 Subtotal - Construction cost 305,500,000.00 [USD 3,818,750]

3.00 Incidental costs

3.10 Professional fees 26,000,000.00[USD 325,000]    10.00% of item 1.16

3.12 Land Cost- [0.25 acres]  KES 50,000,000.00 [ USD 625,000]

OVERALL PROJECT COST 305,500,000.00 + 50,000,000= KES 355,500,000[USD 4,443,750]

INCOME PROJECTIONS

1.10  Accomodation Units

1.11 Projected  price/unit per day KES 2,500 [USD 31.25]

Occupancy rate-90%

1.12 Overall room sales revenue per month=KES 27,000,000[USD 337,500]

1.13 Gross anticipated income per annum[room sales] =KES 324,000,000[USD 4,050,000]

TOTAL GROSS ANTICIPATED INCOME PER ANNUM INCLUDING FOOD AND BEVERAGE SALES =388,800,000.00[4,860,000.00]

1.14 Return on Investment/Repayment period= Approx. 1 year.

LOCATION

South East Commercial Park is a new extension of Nairobi CBD and  is situated within Nairobi's Central Business District along LANDHIES Road. The South East commercial park is served by an all weather road with the site of the proposed construction being found 15 kilometers from the Jomo Kenyatta International Airport.

South East Commercial Park is connected to the mains water supply from the Nairobi City Council and also has easily connected electricity supply.

The immediate locality consists of subdivisions each measuring an eighth an acre. Developments in this area are commercial in nature. The majority of the buildings here are well constructed and maintained.

MARKET DESCRIPTION

Given the proximity of the site to Nairobi's CBD as well as the good communication available, the site would realize good returns on a hotel development.

The site is located 15 km from an International airport and is opposite the largest bus park in East Africa.

The planned development intends to maximize this potential by creating accommodation that is spacious whilst at the same time making optimum use of the space available.

Currently, most Hotels in Nairobi CBD experience a near 100% occupancy rate on a daily basis. The planned development would thus meet an existing need.

COMPETITION

In the locality of the planned development, there are no hotels which cater for the middle class. The closest competition perhaps comes from the low cost hotels in Gikomba area. These are however not impressive in terms of the room sizes and quality of service offered.

SALES PROJECTIONS

It is planned to start marketing the development even as the construction begins.

The room sale price for each unit has been set at KES 2,500[31.25USD]. This is the average charged by comparable hotels such as Kahama hotel in Ngara and Blue Hut hotel along Park road. The price is justified by the upgraded quality of the planned development in terms of finishes, design, and quality of service.

EXECUTION OF THE PROJECT

A4architect will in this provide the client with a full design/build service. This shall include

1. Design and specification

Architectural, structural, mechanical and electrical drawings shall be prepared and necessary approvals sought.

During the various stages of the design, the client shall be kept fully informed and client approval sought prior to proceeding to the next stage. The engineering design shall be done by registered engineers under the guidance of A4architect. Detailed specifications shall be developed with close consultation with the client.

2. Project estimates

Subsequent to completion of the design, a firm estimate shall be done for the project

3. Preparation of tender and contract documents

After final design has been done and client approval obtained, tender documents shall be drawn up for the general and specialist contractors. The specialist contract documents shall be prepared with guidance from the relevant engineers.

4. Tendering

Selected contractors shall be invited to tender for the various work packages. We shall then analyze the tenders returned and forward our recommendation to the client.

5. Contract documentation

With the contractors have been selected, we shall draw up the required contract documents and enter into contract with the contractors on the client's behalf.

6. Project management

Subsequent to the contracts being signed and mobilization to the site, we shall provide superintendence and project management. This will entail ensuring that the project is brought in on time and under budget by constant monitoring of operations on site and remedying any issues that may prevent timely completion or cause expenditure to exceed the budget.

7. Contract administration

We shall handle all matters relating to the various contracts including but not limited to stage payments, performance bonds, extensions of time and relationships between the various traded involved in the project's execution.

8. Sales and marketing

In conjunction with an estate agency approved by the client, we shall produce a presentation package to be used in the sales and marketing of the units.

PROJECT TIMELINES

a) Design to Tender

The design to tender process will take a total of 2 months. This will include commissioning of all engineering design, preparation of bills of quantities and obtaining of all relevant approvals for the development.

b) Construction

Construction of the entire project is estimated to take a maximum of 10 months.

MARKETING AND SALES

Marketing of the properties is planned to start even before ground is broken for the start of the construction. This will serve the dual purpose of creating awareness of the availability of quality hotel service and to confirm the validity of the market intelligence.

A4architect will undertake marketing through the mass media and especially through the internet using a virtual presentation kit that will include a walk through movie of the development.

FEES STRUCTURE

Overall fees charged shall be 10% of the final contract sum. The fees shall be spread over the various stages as follows:

Fees Due

A

Inception

Inception and client brief

Physical survey and information review

Sketch design and basic project proposal

5% of fees.

B

Design and design development

Final design and presentation with budget estimates

Final specifications

Engagement of consultants and preparation of electrical, structural and mechanical services

drawings

Development approvals

30% of fees.

C

Pre-tender process

Preparation of tender documents for general and specialist contractors

Identification of suppliers for client supplied items to be fixed by contractors

Shortlisting of general and specialist contractors

10% of fees.

D

Tender process

Tendering for general and specialist contractors

Tender analysis

Contract award by client on advice of Project Manager

15% of fees.

E

Project Administration

Co-ordination meetings conducted by Project Manager

Close control of work schedule

Monitoring of quality of works and ensuring compliance with specifications

15% of fees.

F

Project Accounting

Budget control

Certification of stage/progress payments

10% of fees.

G

Project closeout

Completion inspection with client

Preparation of final account in conjunction with general and specialist contractors

Preparation of schedule of making good defects

10% of fees.

H

Post contract administration

Final inspection after elapse of defects liability period

Confirmation of making good defects after retention period is over

5% of fees.

Total

100% of fees.

Notes on fees structure

1. Negotiations and any other work arising from the submission of application to the Local Authority or the submission of application to the local authority of the statutory bodies constitutes additional services to be charged for on a time basis.

2. Normalization of contract will be by the signing of both copies of a document mutually agreeable to both parties.

3. Fee notes which will be issued on completion of stage B, C & D respectively. Fee notes for stage (A), & (B) will be based on Project Estimates at those stages.

4. The payment from stages E to H will be based on the final project costs. These will be paid on a pro-rata basis as the project progresses and will be submitted immediately following the issue of certification of contractor stage payments.

5. In the event that the client selects a phased implementation of the project, fee notes for stages A, B and C shall be based on the estimated cost for the entire project while fee notes for subsequent phases shall be pro-rated to the value of the phase being implemented.

6. All fee notes will be processed, authorized and paid within ten calendar days of the fee note date.

7. Reports or opinions requiring formal client approval are to be discussed and approved within five working days of receipt of the request from the project managers by the client.

8. Disbursements resulting from the execution of the consultant's duties including reproduction of drawings and documents, fax messages, traveling and food and accommodation expenses outside Nairobi etc. do not form part of this agreement and will be charged at cost.

Prepared By

Frank Gichuhi

www.a4architect.com

+254 721 410684

A4architect.

Questions and Answers

Ask
200 Characters left
Rate this Article
  • 1
  • 2
  • 3
  • 4
  • 5
  • 0 vote(s)
    Feedback
    Print
    Re-Publish
    Source:  http://www.articlesbase.com/construction-articles/feasibility-study-for-hotel-development-at-south-east-commercial-park-nairobi-cbd-2289831.html

    Article Tags:

    nairobi cbd feasibility hotel south east commercial park

    Frank Gichuhi

    South East Commercial Park is located within Nairobi CBD and has over 140 plots available for sale to developers. These are the only plots for sale available in Nairobi CBD so it gives a great opportunity for a chance to own land and develop commercial property in Nairobi CBD.

    By: Frank Gichuhil Home Improvement> Constructionl May 04, 2010

    Subterranean room water resistant has become well-known as property owners have sought to convert difficult basement area into home.

    By: Persia Walkerl Home Improvement> Constructionl Jun 01, 2012

    If you have a pool in your home, you will want to make sure that the pool maintenance is kept up to date and maintained regularly. Remember that your pool needs to be kept cleaned and tidy at all times but without, the pool could have problems with it that stops you from being able to enjoy it.

    By: Fiona Natalial Home Improvement> Constructionl May 29, 2012

    With the countless electronic devices we use everyday, it is more important now more than ever to take precautions by protecting against lightning and other electrical surges. Surge protection has become much more complex in recent years, therefore it has become much more important. Electronics have become very expensive in recent years, and have also become more vulnerable to surges produced by lightning.

    By: Jeremiahl Home Improvement> Constructionl May 29, 2012

    Stair lifts and elevators can be installed in both new and existing buildings, and go a long way in adding convenience and aesthetic appeal in homes.

    By: Jai Gaitondel Home Improvement> Constructionl May 28, 2012

    Some people don't have enough time to workout because of bad time administration or they're too tired to do any action because of their field of work. If this is your problem then installing a pool is right for you.

    By: Ramon Allenl Home Improvement> Constructionl May 28, 2012
    Frank Gichuhi

    DIFFERENCE BETWEEN LOW, MIDDLE AND HIGH COST FINISHES IN CONSTRUCTION-KENYA Construction costs in Kenya can be divided into 3 categories: Low, Middle and High cost . The main driver of this is the finishes. Generally, all building constructions are broken down into

    By: Frank Gichuhil Home Improvement> Constructionl Sep 01, 2011
    Frank Gichuhi

    KENYAN HOUSING SECTOR-EFFECT OF NEW LOW COST CONSTRUCTION MATERIALS AND METHODS PREFBRICATED HOUSING Prefabricated houses are buildings that are pre-made in the factory and transported to the site where they are bolted up together to form a complete house. Prefabricated panels are in wood, and Structural Insulated Panels. Structural Insulated Panels [SIP] are divided into 3 major types

    By: Frank Gichuhil Home Improvement> Constructionl Sep 01, 2011
    Frank Gichuhi

    THE DIAMOND HOUSE DESIGN-A PARADIGM SHIFT IN EAST AFRICAN ARCHITECTURE ‘The mark of a great architectural design is its ability to influence a paradigm shift from the usual house design to a better design.' Arch. Dr. Mburu-lecturer-JKUCAT

    By: Frank Gichuhil Home Improvement> Constructionl Aug 31, 2011
    Frank Gichuhi

    ADVANTAGES OF USING HAITI HOUSE PLAN BY WWW.A4ARCHITECT.COM 1. It will be easier for potential home owners to be able to plan for construction funding and spending well since the Haiti House plan is standardized and uses unique construction cost reduction techniques. 2. Potential home owners can construct in phases since the Haiti House plan is designed to be built in phase as the income of the house owner grows.

    By: Frank Gichuhil Home Improvement> Constructionl Aug 16, 2011
    Frank Gichuhi

    THE HAITI HOUSE PLAN COSTS BREAKDOWN The Haiti House Plan designed by a4architect.com offers the lowest cost available for construction of houses in Kenya. This is due to the Haiti House© construction technology that uses a holistic approach in reduction of overall construction cost.

    By: Frank Gichuhil Home Improvement> Constructionl Aug 14, 2011
    Author Box
    Articles Categories
    All Categories
    Quantcast