Dr. Chandana Jayalath is a Chartered Quantity Surveyor working at the Public Works Authority on secondment basis.
Any standard form of contract is a generic product applicable under ‘typical’ circumstances subject to amendments in the Particular Application section in order to cater locally specific project requirements where necessary. Importantly, the Contractors therefore recognize the differences and know how to act upon those amendments in the contract. All in all, everyone ‘knows the deal’ if presented with a standard form. The other significant advantage is that the wording of many standard forms has been subject to interpretation over the years by courts. But at least with standard forms both employers and contractors know roughly where they are standing. There are always those who wish to go down the bespoke route but even in bespoke contracts there are vast chunks of texts copied straightway from standard forms. Even though on most occasions what the standard form gives with one hand the amendments take back with the other.
Some construction clients (employers) have either seriously amended or loosely deleted some of the standard provisions given in the General Conditions. For instance, the FIDIC forms that have been extensively adopted in construction projects in the Middle East have been heavily amended to suit the local conditions by inserting new clauses or deleting some of the key sensitive clauses, such as claims, time extension, price fluctuation, local authority delays etc. This not only tilts the apportionment of risks but adulterates the real taste and rhythm of FIDIC in its own right. They are no longer FIDIC in that sense, and as a result of this customization via cut and paste exercise, it is mostly employers themselves who find in trouble.
This trend is apparently because some employers falsely assume that by deleting or amending the employer is getting immunity from potential claims. Unfortunately, this logic is flawed and deletion or improper amendment of such clauses is disadvantageous and, in some cases, even dangerous for employers and unhealthy for projects in long run.
The thumb rule is that if the Contractor does not have an entitlement within the Contract, he may well raise a claim outside the confines of the same, if there is an overriding statutory provision. Contracts are construed in accordance with the local provisions pertaining to governance of commercial contracts. Deletion therefore does not necessarily mean that no one is entitled or is loosing any right to claim, but it would obviously mean that the contract is silent in the issue, where the disgruntling party would definitely seek a resolution in the next available route, either by referring to similar case law or standard norms of the building trade. More over, in most jurisdictions, it is legally possible for a Contractor to raise a claim outside the contract if he has been hindered by the Employer for instance in line with the Prevention principle, which obliges both parties to co-operate and not hinder the other from fulfilling his obligations. This is applicable even if the Contract does not have a ‘claims clause’.
Furthermore, if there is no extension of time clause in the contract, the Contractor could also raise a ‘time at large’ argument (if he is delayed by the Employer) which would render the contractual completion date null and void. If time does become at large, the Contractor is only obliged to finish the Contract within a ‘reasonable’ period of time which would obviously put the Employer in embarrassment.
Another example is that, many standard forms require the Contractor to submit a notice within 28 days and he is also obliged to maintain contemporary records and submit regular interim particulars to support his claims. If the Contractor does not submit a notice within 28 days, his claim could be ‘time barred’ and he could lose his rights to an extension of time and/or other entitlements. If this time frame has been amended with the phrase such as ‘as soon as practicable’, it does not amount to a condition precedent to lodge a claim but results in an open-ended time frame that requiring a technical interpretation prior to establish the eligibility of the claim.
Also, silence is more dangerous than deletion. The premise behind this line of thinking is that the parties have taken on board the risk of deletion at the time they entered into the contract itself, but silence may sometimes purport acceptance or refusal, as the case may be. The classic case is price fluctuation. For instance, the majority of contractors in the Middle East have been locked into lump sum fixed-priced contracts where there is no provision for price escalation. Open market vacillations are a risk to the contractors, even in contracts having long durations. However, the recent surge in material costs has considerably affected their bottom lines where profit margins are not as high as they once were. As a result, contractors have been searching for recovery means, of course through claims on their own basis. Many contractors use consumer price index (CPI) as the basis of claim although the purpose of the index is far different. The only way to get rid of this issue is to compensate the additional cost on ex-gratia basis, however because the eventualities are so global and unprecedented.
The aim behind any strategy should be to reasonably reimburse the contractor for changes in input prices over which they have no control at all. This means the contractor can be eligible only under those eventualities he could not reasonably foresee in advance simply because the contractor shall allow for possible increases in the prices during contract period via the rates quoted. On the other hand, it may be cheaper in long run for the employer to pay for what did happen rather than what the contractor thought might happen in those areas of doubt which the contractor can not influence. The benefit of the doubt would then be passed on to the employer in a deflation. It will also overcome the risk of providing an additional mark-up with a view to compensate for the unforeseen price variations and avoid strategic manipulations and claims at large.
Another case is termination for convenience clauses that are intended to provide the employer with the option to terminate the remaining balance of the contracted for work for a reason other than the contractor’s default. For example, if the employer cannot obtain additional financing to complete the work, the employer can terminate the balance of the work for convenience so long as there is a termination for convenience clause in the contract. However, if the contract does not contain a termination for convenience clause, and the employer terminates the contract before the work is complete, then the contractor would be entitled to the value of the work completed plus a reasonable profit margin that he or she would have earned on the balance of the contract.
In every contract there is an implied covenant of good faith and fair dealing. Therefore, it can be argued that if the termination for convenience clause is exercised in bad faith, the termination may be a breach of contract. For example, if the employer chose to exercise the termination for convenience clause when the project work was ninety percent complete in order to avoid paying the balance of the profit on the remaining contract work, the termination could be held to be a bad faith termination and constitute a breach of contract.
Employers must therefore take utmost care in amending typical standard clauses when they customize their contracts so as to avoid backfiring, especially the impact a change to one clause may have to the rest of the contract. Those amending contracts must always have in the back of their minds the contra-preferentum rule. Essentially it provides that if there is an ambiguity in a document which means a clause could have two alternative meanings, then a court may construe the words against the party who put the document forward (i.e. usually the employer) to give effect to the meaning more favorable to the other party. This can be a significant risk for employers.
The case of Balfour Beatty Civil Engineering Ltd v Docklands Light Railway is a good example of the dangers involved in amending standard forms. In this case the contract was an ICE 5th Edition, but two significant amendments had been made. Firstly, the independent engineer was replaced by an Employer’s Representative and, secondly, the clause 66 dispute provision had been deleted entirely. It is important to note that had the arbitration clause not been deleted it would have contained the right of the arbitrator to ‘open up, review and revise decisions of the contract administrator’. Given the clause had been deleted, did the court have the power to open up, review and revise decisions of the Employer’s Representative? The court held that they did not have such power and the contractor’s entitlement to payment and extensions of time was dependent on the judgment of the Employer’s Representative. Whilst it was held that the Employer’s Representative had a duty to act honestly, fairly and reasonably, the court held that there was no means of contesting the Employer’s Representative’s decisions and that they became final and binding.
Hence, it is always better not to touch the General conditions but to have proper amended clauses as long as the primary intension of the standard clauses are secured in the given the General section.
- Related Videos
- Related Articles
- Ask / Related Q&A




Leeds Solicitors - How to Choose the Right Leeds Solicitor for your Case
By: Michiel Van Kets | 22/12/2009Having legal problems is one of life's more stressful situations but having expert legal counsel in the form of a Leeds solicitor can make things much easier and give your real peace of mind. Proper legal advice can save you a lot of time and worry whether making a will, buying or selling a home, or dealing with employment-related legal problems in the Leeds area.
Do You Know Texas Law For DUI Charges?
By: Rudy Silva | 22/12/2009Do you want to know how to handle DUI charges? Each state has its own DUI laws. Driving under the influence of alcohol is a felony in Texas. Your involvement to DUI charges might give you headaches. If you need a free lawyer, the state can provide one for you. The state also has recovery programs. Read this article to learn about to solve your DUI charges.
Drug Crimes Are Not Only a Grown-up Problem Anymore
By: Adriana N. | 21/12/2009There was once a time when drug crimes mainly affected grown folks, and people did not have to worry so much for their kids. But as the years have passed, crimes involving drugs are including younger and younger age groups. The following paragraphs will provide some useful advice regarding keeping...
4 Questions to Ask a Personal Injury Lawyer
By: Thomas Butler | 21/12/2009Important questions to ask a personal injury lawyer to ensure that they're experienced and qualified to handle your legal situation.
How are Criminal Records Classified?
By: Kevin Jones | 21/12/2009How to classify different types of criminal records.
Criminal Records Classification
By: Kevin Jones | 21/12/2009Description of all the different types of criminal records.
What should I bring when I meet with the attorney handling my personal injury lawsuit?
By: Evan Gewirtz | 21/12/2009Being involved in a serious accident can be painful and confusing. This article includes tips on what a lawyer will need if you are thinking about filing an accident injury lawsuit.
How Do I Check Criminal Court Records Free To Access Someones Criminal History
By: James Nash | 21/12/2009If you want to find criminal history of a specific person you don’t have to deal with regulations and paperwork if you don’t really want to. You can just search for criminal court records from your own home using the internet.
Claims on Prolongation Costs in Nutshell
By: Dr. Chandana Jayalath | 03/11/2009 | ConstructionThe use of preliminaries on pro rata basis would not truly result the actual loss in prolongation. The level of compensation is what is reasonable in the circumstances. Each case shall be evaluated on its own merit.
Application of Causation, Remoteness and Foreseeability Tests in Determining Eligibility of Claims
By: Dr. Chandana Jayalath | 29/10/2009 | LawIt is a cumbersome exercise to be dealt with far remote facts, both for justification and evaluation.
Amendment, Deletion or Silence – Which One is Better?
By: Dr. Chandana Jayalath | 28/10/2009 | LawIt is always better not to touch the General conditions but to have proper amended clauses as long as the primary intension of the standard clauses are secured in the given the General section.
Claims for Loss of Profit on Omitted Works in Nutshell
By: Dr. Chandana Jayalath | 25/10/2009 | LawIf, however the instruction omitting works is a valid variation order, then whether a contractor can claim loss of profit on such omitted works depends upon the wording of the conditions of contract.
Termination Claims in Nutshell
By: Dr. Chandana Jayalath | 25/10/2009 | LawThere are two general types of termination typically addressed in construction contracts: termination for convenience and termination for cause (sometimes referred to as termination for default).
Recovery of Unabsorbed Head Office Overheads in a Contract Prolongation
By: Dr. Chandana Jayalath | 25/10/2009 | LawIt is impossible to accurately measure any under absorption of head office overheads whenever the damages become too remote and speculative. However, the contractor’s entitlement as to claim for additional overhead costs has been confirmed in case law.
Dealing with Suspension Claims in Nutshell
By: Dr. Chandana Jayalath | 25/10/2009 | LawA party, who wishes to exercise the right to suspend performance, runs the risk that their suspension will be regarded a failure to carry out the works regularly and diligently and may be treated as a repudiation of the contract, if in the particular circumstances no such right actually exists.
Dealing with Quantum Meruit Claims in Nutshell
By: Dr. Chandana Jayalath | 25/10/2009 | LawIn establishing a quantum meruit claim, the claimant must prove the total costs incurred and payments made by it in carrying out the works. The claimant must also establish that the amounts in question were fair and reasonable in the circumstances.