Whenever variations are ordered that omit work, and particularly if such omissions are substantial in nature, contractors often argue that they should be entitled to claim the loss of profit that they would have earned on such works.
If the variation omitting works is invalid then such is a breach of contract entitling the contractor to damages, and it is clearly established that loss of profit can form part of such a claim for damages. It is breach of contract and not a valid variation when the works have been omitted and given to others to carry out. This point has been confirmed in the case of Gallagher v. Hirsch NY App Division 467 (1899) where the American court held that the word "omission" meant only work not to be done at all, not work to be taken from the contractor and given to another to do. Secondly, where the power to order variations set out in the contract has been exceeded. (Variations must be either necessary or desirable for the satisfactory completion or functioning of the works). Works can not be omitted for example, to save time for completing the works, or to save the employer’s money.
If, however the instruction omitting works is a valid variation order, then whether a contractor can claim loss of profit on such omitted works depends upon the wording of the conditions of contract. Many standard forms provide: "The prices in the Contract Bills shall determine the valuation of items omitted; save that if omissions substantially vary the conditions under which any remaining items of works are carried out." This provision is not helpful to a claim for loss of profit, because it provides that the omitted works must be valued at the rate in the Contract Bill, i.e. omitting the full value, including profit, of the item in the Contract Bills. Nor is the proviso of any assistance in such a claim because the variation must substantially vary the conditions under which the remaining items are carried out before the remaining items can be re-valued.
Loss of profit on an omitted item will not in itself vary the conditions in which the remaining items are carried out. So the proviso does not appear applicable in this situation. However, contracts typically provide the Contractor with an entitlement to claim 'direct loss and/or expense' incurred by reason of a variation. In the case of Wraight Ltd v. P H and T Holdings (1968), a contract was wrongly determined with the work part completed. The determinations clause provided for the contractor to be paid "Any direct loss and/or damage caused to the contractor by the determination." It was held by the court that this wording included loss of gross profit on the uncompleted work. Therefore, following the Wraight case it would appear arguable that a claim for loss of profit on works omitted by way of a variation can be claimed as direct loss and or expense.
Many standard forms provide for re-rating other items in the Bills of Quantities if a variation renders such rates inapplicable or unreasonable. However it is again not considered possible to argue that this power extends to re-rate other items in the Bills of Quantities on the basis that there has been a loss of profit on works omitted. A variation omitting works would not normally cause a disturbance to progress. In conclusion therefore, whilst a claim for loss of profit will always be successful where the works were omitted by way of an invalid variation order, where the variation is valid it seems clear that many contracts do not provide a means for a contractor to claim for loss of profit on works omitted. However such a claim is possible as a direct loss and expense claim on the basis of the decision in the Wraight case.
Generally, for contractors seeking to prove a claim of lost profit due to omitted scope, it is critical to demonstrate that his loss of profit by the omission of work is genuinely incurred because his inability to recover that loss elsewhere. It is not sufficient to simply argue that the lost profit is speculative on the basis of a profit allowance in tender, ie loss of profit = value of omitted work x 15% profit margin for instance. However, this is a cumbersome exercise to be dealt with far remote facts, both for justification and evaluation. On the other hand, importing case law from different jurisdictions will definitely have legal ramifications. It could also be argued that the parties have entered into contract clauses together with their repercussions taken to have already agreed unless the contract expressly forbids or provides for.
- Related Videos
- Related Articles
- Ask / Related Q&A
- Claims for Loss of Profit on Omitted Works in Nutshell
- Calculating a Claim For Loss of Profits
- Join an Online Trading Community to Convert Losses Into Profits
- Turn Weight Loss Into Profit
- United Kingdom: Theory Into Action: Calculating Damages Payments and Accounts of Profits in Patent Cases
- Big Pharma Petition the FDA to Ban Natural Weight Loss Supplements
- American Airlines Reports First Quarter Losses
- Free Weight Loss Pills-Do They Really Work?




Intestacy rules and surviving spouses
By: Bob Brightside | 05/01/2010When a person dies without a valid Will, the law says he or she has died ‘intestate’. This means any money and belongings left will pass under the statutory rules of intestacy. These rules set out in detail who will receive what, depending on which family members are still living.
Where Can I Find Public Court Records In Minnesota To View Someones History
By: James Nash | 05/01/2010Finding someone’s history isn’t tiresome process as it was few years back. This is all thanks to the technology and development of internet. This means that today you can find public court records on the internet and find all information about someone’s history that way.
Reasons for Beverly Hills Attorneys
By: Soby Singh | 05/01/2010People, Who Deal with Divorces and Accidents There are different happenings in our lives and sometimes we just need legal assistance from real specialists. Beverly Hills, although it looks like a “heaven on Earth”, same as any other place in the world, has divorces and personal injury accidents. Luckily, Beverly Hills personal injury and family laws are supported by people who really comprehend all the peculiarities of these complex laws.
Update Your Landscaping When Selling Your Home
By: Eva Judge | 05/01/2010Performing a few renovations and other home improvement projects is a smart idea when you want to put your house on the market. By making it look its absolute best, you'll be able to ask for more money. However, focusing only on its interior isn't good enough - you need to take its landscaping into consideration, as well.
Can You Lookup Public Court Records On The Internet To See A Persons Criminal History
By: James Nash | 05/01/2010If you want to find a person’s criminal history for some reason the best source for that kind of info might be court records. They are part of public records, but obtaining of those can take some time. If you want to find desired records the best solution might be to search them on the internet.
Use Landscaping To Increase Your Home's Value
By: Eva Judge | 05/01/2010Performing a few renovations and other home improvement projects is a smart idea when you want to put your house on the market. By making it look its absolute best, you'll be able to ask for more money. However, focusing only on its interior isn't good enough - you need to take its landscaping into consideration, as well.
Federal Employees Workers Compensation Claims
By: Jason | 05/01/2010U.S. government employee worker’s compensation claims are administered under the Federal Employment Compensation Act (FECA), handled separately from state worker’s compensation law.
Divorce Writer
By: diovorcewriter | 05/01/2010In recent years statistics have shown that there has been a steady rise in the amount of divorces taking place.
Claims on Prolongation Costs in Nutshell
By: Dr. Chandana Jayalath | 03/11/2009 | ConstructionThe use of preliminaries on pro rata basis would not truly result the actual loss in prolongation. The level of compensation is what is reasonable in the circumstances. Each case shall be evaluated on its own merit.
Application of Causation, Remoteness and Foreseeability Tests in Determining Eligibility of Claims
By: Dr. Chandana Jayalath | 29/10/2009 | LawIt is a cumbersome exercise to be dealt with far remote facts, both for justification and evaluation.
Amendment, Deletion or Silence – Which One is Better?
By: Dr. Chandana Jayalath | 28/10/2009 | LawIt is always better not to touch the General conditions but to have proper amended clauses as long as the primary intension of the standard clauses are secured in the given the General section.
Claims for Loss of Profit on Omitted Works in Nutshell
By: Dr. Chandana Jayalath | 25/10/2009 | LawIf, however the instruction omitting works is a valid variation order, then whether a contractor can claim loss of profit on such omitted works depends upon the wording of the conditions of contract.
Termination Claims in Nutshell
By: Dr. Chandana Jayalath | 25/10/2009 | LawThere are two general types of termination typically addressed in construction contracts: termination for convenience and termination for cause (sometimes referred to as termination for default).
Recovery of Unabsorbed Head Office Overheads in a Contract Prolongation
By: Dr. Chandana Jayalath | 25/10/2009 | LawIt is impossible to accurately measure any under absorption of head office overheads whenever the damages become too remote and speculative. However, the contractor’s entitlement as to claim for additional overhead costs has been confirmed in case law.
Dealing with Suspension Claims in Nutshell
By: Dr. Chandana Jayalath | 25/10/2009 | LawA party, who wishes to exercise the right to suspend performance, runs the risk that their suspension will be regarded a failure to carry out the works regularly and diligently and may be treated as a repudiation of the contract, if in the particular circumstances no such right actually exists.
Dealing with Quantum Meruit Claims in Nutshell
By: Dr. Chandana Jayalath | 25/10/2009 | LawIn establishing a quantum meruit claim, the claimant must prove the total costs incurred and payments made by it in carrying out the works. The claimant must also establish that the amounts in question were fair and reasonable in the circumstances.