Suspension usually occurs on a construction project when an employer requires a contractor to temporarily stop work on all or a portion of the project. Contractually, the contractor shall suspend the progress on the engineer’s written notice if it is only provided for in the contract, due to contractor’s default, due to climatic conditions, on safety reasons, necessary for proper execution of work or in excepted risks. A mandatory requirement is cast on the contractor to give a written notice of his intension to claim for any additional cost or time within a specified period from the date of receiving the engineer’s order to suspend the work. This clause specifically permits the engineer to authorize extension of time or payment of extra cost, whose decision is final and binding.
The cost shall be borne by the employer unless such suspension is otherwise provided for in the contract, necessary for the proper execution of the works, by reason of weather conditions that affecting quality or safety, buy some default on the part of the contractor or necessary for safety of works.
The typical clause ‘suspension lasting more than 90 days’ is to deal with suspension in one-go or part by part in consecutive periods, giving the contractor the right to determine the contract in two ways. If the suspension under Sub-Clause 8.8 [Suspension of Work] has continued for more than 84 days (in FIDIC), the Contractor may request the Engineer’s permission to proceed. If the Engineer does not give permission within 28 days after being requested to do so, the Contractor may, by giving notice to the Engineer, treat the suspension as an omission under Clause 13 [Variations and Adjustments] of the affected part of the Works. If the suspension affects the whole of the Works, the Contractor may give notice of termination under Sub-Clause 16.2 [Termination by Contractor]. It will be sometimes treated as an abandonment of the contract by the employer.
After the permission or instruction to proceed is given, the Contractor and the Engineer shall jointly examine the Works and the Plant and Materials affected by the suspension. The Contractor shall make good any deterioration or defect in or loss of the Works or Plant or Materials, which has occurred during the suspension.
Suspension claims often require a schedule delay analysis to evaluate the impact to the project’s critical path. A suspension claim will consist of cost calculations with regard to protection and securing works, idling labor, plant etc, loss of managerial inputs and any other incidental costs such as costs on demobilization/remobilization costs and other actual costs incurred due to the suspension. In addition, if the employer’s actions do not allow the work to proceed but the suspension clause has not been invoked, the contractor may claim for constructive suspension.
A party, who wishes to exercise the right to suspend performance, runs the risk that their suspension will be regarded a failure to carry out the works regularly and diligently and may be treated as a repudiation of the contract, if in the particular circumstances no such right actually exists. The right to suspend performance for non-payment is statutory but the parties are free to agree how long the period is between the date on which a sum becomes due and the final date for payment of that sum, then the period will vary between contracts.
- Related Videos
- Related Articles
- Ask / Related Q&A
- Air Bag Suspension Technology Replace Mechanical Leaf Springs
- Advantages Of Dual-Suspension Mountain Bike
- Having a Suspension Lift Kit
- Suspension Springs Manufacturers – Makes Riding Easy
- Motorcycle suspension-mastering a black art
- Suspension Bushes: Because Your Car Deserves Great Speed
- Your Kit on Suspension Lift Kit
- Suspension Bushes: Friend of a Car on Tough Roads




Chinese Drywall - The Great Drywall of China Problem
By: Dave H | 24/12/2009Chinese Drywall - it's all over the news. Like a plague with devastating effects, its mere mention can wipe out home values in affected communities as homes are considered guilty by association. What exactly is the problem?
HOW KEEPING PROPER MEDICAL RECORD DOCUMENTATION AND AVOIDING PROBLEMATIC BILLING AND CODING PRACTICES MAY REDUCE THE RISK TO YOUR NEW YORK MEDICAL PR
By: Joseph Potashnik | 24/12/2009Medical billing is essential in the practice of medicine. Just like everyone else, doctors want to be paid for their services. While timely and proper billing is the key to financial success and stability of a medical practice, improper billing practices may get a physician in trouble beyond any imagination. Medical billing and keeping medical records are two absolutely interrelated areas and proper documentation maintenance is crucial to avoiding many billing issues.
*CONTRACT TO BUY A CONDOMINIUM UNIT - WHAT TO LOOK OUT FOR?
By: DAVID TAN | 24/12/2009You are requested to sign a sale of condominium unit contract, what contractual conditions should you look out for?
Where Can You Retrieve Divorce Records Free Of Charge To Check Peoples Background
By: James Nash | 24/12/2009When it comes to finding divorce records there are some good news. You can now find them, free of charge on the internet and save precious time and money. Sounds interesting ? Well, why don’t you give it a try?
Violent and Property Crime Statistics
By: Richard Armen | 24/12/2009Just how likely are you to become a victim of crime? It is believed that crime is increasing in many cities across the United States. Most of the country's large cities, from New Orleans to Los Angeles and everywhere in between, have disturbingly high numbers of violent crime (which include...
Where Can I Locate Court Records Free Of Charge To Access Peoples Past
By: James Nash | 24/12/2009If you want to check people’s past you can do it in so many different ways. You can find it at the courthouse, but why wait in long lines for single court record when you can find it online faster than before?
Have You Heard of Litigation Support Services - What is This
By: Adriana Noton | 24/12/2009Have you heard of litigation support services? This is a litigation service which helps lawyers present a better case. The better your case the better chance you have to win. Many cases do not get to the trial stage. They are negotiated before trial and both parties agree to a...
FDA Panel Finds Increased Risk with Some MRI drugs
By: Katie Kelley | 24/12/2009A recent FDA panel has found certain MRI imaging drugs have an increased chance of causing the potentially fatal skin disease Nephrogenic Systemic Fibrosis.
Claims on Prolongation Costs in Nutshell
By: Dr. Chandana Jayalath | 03/11/2009 | ConstructionThe use of preliminaries on pro rata basis would not truly result the actual loss in prolongation. The level of compensation is what is reasonable in the circumstances. Each case shall be evaluated on its own merit.
Application of Causation, Remoteness and Foreseeability Tests in Determining Eligibility of Claims
By: Dr. Chandana Jayalath | 29/10/2009 | LawIt is a cumbersome exercise to be dealt with far remote facts, both for justification and evaluation.
Amendment, Deletion or Silence – Which One is Better?
By: Dr. Chandana Jayalath | 28/10/2009 | LawIt is always better not to touch the General conditions but to have proper amended clauses as long as the primary intension of the standard clauses are secured in the given the General section.
Claims for Loss of Profit on Omitted Works in Nutshell
By: Dr. Chandana Jayalath | 25/10/2009 | LawIf, however the instruction omitting works is a valid variation order, then whether a contractor can claim loss of profit on such omitted works depends upon the wording of the conditions of contract.
Termination Claims in Nutshell
By: Dr. Chandana Jayalath | 25/10/2009 | LawThere are two general types of termination typically addressed in construction contracts: termination for convenience and termination for cause (sometimes referred to as termination for default).
Recovery of Unabsorbed Head Office Overheads in a Contract Prolongation
By: Dr. Chandana Jayalath | 25/10/2009 | LawIt is impossible to accurately measure any under absorption of head office overheads whenever the damages become too remote and speculative. However, the contractor’s entitlement as to claim for additional overhead costs has been confirmed in case law.
Dealing with Suspension Claims in Nutshell
By: Dr. Chandana Jayalath | 25/10/2009 | LawA party, who wishes to exercise the right to suspend performance, runs the risk that their suspension will be regarded a failure to carry out the works regularly and diligently and may be treated as a repudiation of the contract, if in the particular circumstances no such right actually exists.