Richard G. Ligus is President of Rockford Consulting Group located in Rockford, IL., with over 30 years experience in manufacturing, procurement, transportation and distribution. He specializes in developing and implementing supply chain strategies. Rich is an author and a speaker, and has developed seminars with the American Management Association. He is certified by both the Institute of Management Consultants and the The National Bureau of Certified Consultants.
Rich has a bachelor of science degree in mechanical engineering from the New Jersey Institute of Technology, and a master of business administration degree from Rutgers University. He is a member of CASA/SME, and has been listed in Jane's Who's Who in Aviation and Aerospace. He has been a speaker at IMTS, USCTI, APFA, NEPMA, MCAA, Hand Tools Institute, CASA/SME, and others. He has appeared several times on WREX-TV, Mid-Morning Magazine.
The 12 Cardinal Sins of ERP Implementation
Introduction
Enterprise Resources Planning (ERP) is an outgrowth of Material Requirements Planning (MRP) initiated in the 1970's as a new computer-based approach to planning and scheduling of material requirements and inventory, featuring the time-phased order point. MRP evolved to MRP II (Material Resources Planning) the "closed loop" process, to Business Requirements Planning (BRP) and eventually to ERP. As MRPII came into vogue in the late 1970's and early 1980's, software companies began to develop software packages around MRPII concepts.
At the same time, research of integrated data bases was in progress at a university, and out of that research emerged data base management systems (DBMS). One of the earliest successful commercially-produced data base management systems was IDMS (for IBM-based systems) and DBMS (for DEC-based systems) produced by Cullinane, who's company name was later changed to Cullinet. IMS, a structured data base management system for high transactions, was another data base management system produced by IBM.
The idea of the integrated data base as the engine for fully integrated software was probably one of the greatest outgrowths of Ollie Wight's and Dave Goddard's MRP. Eventually, the acronym ERP was conceived to represent what had already been developed by software companies.
The early software packages were developed by way of a transactional approach, and were highly unfriendly to a user. With the advent of the personal computers, the development of Microsoft's Windows NT, and the mid-range IBM AS/400 computer, client-server systems began to emerge. Windows, used as the base operating system, allowed software packages to become more and more user-friendly.
Today, ERP systems have proliferated extensively, and have reached a stage where development has become industry specific. Thus it is plausible to search for an ERP package developed for one's specific industry idiosyncracies.
The Issues
The biggest single issue in ERP is the failure of a successful implementation. It is mind-boggling to continually encounter companies who make major ERP gaffes in this day and age, especially since most of the trials and tribulations of MRPII implementation were suffered and learned from in the early 1980's with alpha, beta and gamma releases.
So what constitutes failure? Several things come to mind:
(1) Not making the promised return on investment,
(2) Inordinately extending the implementation schedule and start-up date,
(3) Running over budget by unconscionable variances,
(4) Grinding the organization to a crawl pace, or the severest of all consequences,
(5) Stopping production and/or not delivering orders to your customers.
Industry statistics show that >60% of ERP implementation starts historically fail. Does this mean that you are doomed from the start? Of course not, if you learn from the mistakes of others. So the pertinent question is what are the main causes of ERP failure and what can be done to prevent this from happening to you?
The 12 Cardinal Sins of ERP Implementation
There are twelve major reasons for why companies get bogged down or fail in implementing ERP.
(1) Lack of Top Management Commitment
The propensity of top management to delegate the oversight of an ERP implementation to lower management levels often results in (1) being "out of touch" with critical events, or (2) the lack of understanding of the size, scope, and technical aspects of the project, and subsequently, the lack of proper commitment of time and resources required for a successful implementation. The result is a failure waiting to happen.
(2) Inadequate Requirements Definition
Surveys have shown that inadequate definition of functional requirements accounts for nearly 60% of ERP implementation failures. This is simply a matter of not comprehensively and systematically developing a quality set of functional requirements definitions. This leads to the second greatest cause of ERP implementation failures: poor package selection.
(3) Poor ERP Package Selection
Poor package selection occurs when a company has inadequately developed functional requirements definitions. It also occurs when staff members assigned to ERP projects do not take the time to run the screens of the new system, as they would during their daily work tasks, to find out if the software package features are adequate for their needs.
Another reason we have found is executives, familiar with an ERP system from a last job they held, implement the same system in their new company without defining functional requirements. We have also encountered companies who made major gaffes by selecting a package at the top levels of a company without intimately knowing its characteristics. What often results from this is the ERP package doesn't fit the organizational needs, or that the package selected takes longer to process daily work tasks.
We have also seen executives select a distribution package for a manufacturing environment, or a manufacturing package for a distribution environment, for obscure reason, such as liking one salesman over another.
(4) Inadequate Resources
The third greatest reason for ERP implementation failures is inadequate resources. Many companies will attempt to "save dollars" by doing everything on an overtime basis, whether or not there are adequate skills within the company, extending individual work loads to 150%. This approach can be a "kiss of death" for the program. Time and time again we run across this mistake in ERP implementations. The financial and emotional drain of what seems sometimes to be perpetual extensions, reschedules and delays of implementations takes its toll. People burn out after having put in extensive hours over a long period of time.
(5) Resistance to Change/Lack of Buy-in
The lack of a change management approach as part of the program can prevent a program from succeeding. Resistance to change is quite often caused by (1) A failure to build a case for change, (2) Lack of involvement by those responsible for working with changed processes (3) Inadequate communication (4) Lack of visible top management support and commitment, and (5) Arrogance. A lack of buy-in often results from not getting end-users involved in the project from the very start, thereby negating their authorship and ownership of the new system and processes.
(6) Miscalculation of Time and Effort
Another cause of ERP implementation failure is the miscalculation of effort and time it will take to accomplish the project. Companies who treat an ERP selection, evaluation and implementation comparable to buying a washing machine are doomed to failure.
(7) Misfit of Application Software with Business Processes
One of the main causes of ERP implementation failure is the misfit of application software with the company business processes. This failure -- to examine underlying business process flaws, and integrate the applications with the business processes, causes loss of productivity and time, and ultimate benefits.
(8) Unrealistic Expectation of Benefits and ROI
Another significant cause for ERP implementation failure is the unrealistic expectation of benefits and return on investment. Software providers are notorious for overstating the benefits in terms of ROI, when the total costs of the project have been understated. Often left out of the total costs are costs of planning, consulting fees, training, testing, data conversions, documentation, replacement staffing, and the learning curve performance drop. When this happens, a company doesn't stand a chance of achieving the ROI it anticipated.
(9) Inadequate Training and Education
Another of the biggest causes of ERP implementation failure is inadequate education and training, which are almost always underestimated. ERP-related training is crucial as most employees must learn new software interfaces and business processes which affect the operation of the entire enterprise. The corporate culture is impacted by changes in the company’s business processes, and shortchanging this part of the ERP implementation leads to much pain and suffering downstream.
(10) Poor Project Design and Management
A major mistake is to short-cut critical events in the project plan, such as time for documentation, redefining and integrating processes, or testing before "going live."
Another common mistake is made when a company leaves out the self-examination of business processes and uses ERP to cover-up weaknesses. It is easier to buy software than to perform the more difficult task of identifying weaknesses and opportunities for improvement.
(11) Poor Communications
One of the causes of ERP implementation failure is poor project communications, beginning with a failure to announce the reason for the up and coming effort, and continuing to advise the organization of the progress and importance of the ERP implementation to the company. Poor communications prevent different parts of the organization from assessing how they will be impacted by changes in processes, policies, and procedures. Communications are a vital part of managing change in a corporate environment.
12) Ill-advised Cost Cutting
Another of the key causes of ERP implementation failure is ill-advised cost cutting. In an effort to avoid temporary conversion costs, some companies take a very risky route and go live at multi-plant sites simultaneously, subjecting all plants or some plants to a total shutdown should there be a false start-up. This is suicidal. Others attempt to unrealistically compress the schedule in order to save on expenses, only to eventually overrun both schedule and budget. We feel that ROI should take a "back seat" when upgrading an important part of a company's infrastructure: the information system. Instead the implementation should be treated as an upgrade to the company infrastructure that is necessary to maintain or gain a strategic and competitive advantage.
Pragmatic Applications
The first corollary of ERP or information systems implementation is:
Information systems are part of a company infrastructure, and therefore are strategic to the company's survival and success.
If a company does not consider IS as one of its critical success factors, chances are, the competition does.
The second corollary of ERP or information systems implementation is:
ERP and information systems are there to support business functions and increase productivity, not the reverse.
The driver for an ERP implementation should be to increase a company's competitiveness, not the adoption of a new religion that bends or distorts how a company conducts its business.
The third corollary of ERP or information systems implementation is:
Learn from the successes and failures of others and don't attempt to reinvent the wheel of ERP implementation practice.
There are time-proven approaches that can enhance the success of the ERP implementation. Here are a few:
High Employee Involvement
Get as many employees to participate heavily as practicable in accomplishing the functional requirements definition. The workers know their work and what they need to compress time. If they do not, use an outsider who does. Use a knowledgeable team to review and select packages. Get as many employees as practicable involved in the implementation phase. This will foster ownership and buy-in.
A Comprehensive and Systematic Approach
Use a comprehensive and systematic master plan that addresses all parts of an ERP systems implementation: development of IT strategy, requirements definition, review/selection of software, hardware, communications, unit testing, systems testing, conversion, resources, education/training, resistance to change, etc.
Adequate Resources
Provide adequate technical and administrative resources to allow employees breathing room. Perform cost/benefit analyses so that you know how much the entire implementation is going to cost and identify the results that will be achieved.
Extensive Education & Training at all Levels
Provide adequate training for most employees, including upper and middle management.
- Related Articles
- Related Q&A




Personal Organisers Can Be a Stylish and Up to Date Promotional Item
By: Jeff McDougall | 29/12/2009If you have ever been the recipient of a new year compliment from a number of your customers, it would most probably be a personal organizer, key chains, calendars or the new age pen drives. Personal organizers have been the most common of all gifts across many organizations. This, given...
How Ergonomic Office Furniture Can Help a Company Make More Money
By: Jeff McDougall | 29/12/2009The benefits of an ergonomically designed office are far too many to ignore. The use of ergonomic furniture setup in an organization has immense advantages from the management perspective as well as from the employees. One cannot but discount that the comfort levels of the employees is very significant...
Conference Calls or Business Travel - What’s in your budget this year?
By: James K King | 29/12/2009The debate between businesses using conferencing technologies to deliver effective communication with their clients versus the expense and environmental concerns of large scale business travel in today’s trading environment.
The Online Automatic Cash Machine Making Over $15,000 Per Month on Internet Marketing on Automatic Cash flow
By: Dale Dupree | 29/12/2009You begin slow, then you make a little bit of cash a week, then rinse and repeat and you make a little bit more, and you go building your business and the number of sites you own and so on. Then your income will start increasing slowly and steady Money will not pour into your bank account like magic and you can't spend every dollar you make on bills. You must to grow your business by re-investing what you
Change management
By: Fleur Gardner | 29/12/2009It is often seen that people are averse to change. They do not want change of work profile or change in ways to work or change in command. Every time they are presented with a situation demanding change, they tend to delay or avert the situation, rather than working towards change management.
Five Core Team Building Activities
By: Chris Gill | 29/12/2009The Xpeerience Group describes five core team-building activities, from sports to music.
5 ive Questions Every Professional Career or Business Plan Should Answer
By: Maria Marsala | 29/12/2009A good plan today is better than a perfect plan tomorrow. – Proverb A perfect plan won’t ever happen. What you need instead is a “working plan” that is focused, concise, and easy to change!
Customer Relationship Management is a fast growing market in China
By: Bharat Book Bureau | 28/12/2009Bharatbook.com added a new report on "Customer Relationship Management (CRM) Market in China 2008-2012" forecasts the size of the Customer Relationship Management (CRM) market in China.
Get Your Assembly Equipment For Free: How To Propose a Winning Capital Equipment Justification
By: Richard G. Ligus CMC CPCM | 02/04/2009 | ManagementTo increase productivity and competitiveness, many companies have adopted Lean and Continuous Improvement philosophies. But there is a point that is reached that in order to make substantial gains in productivity and performance, new equipment is needed for various reasons such as faster cycle times and increased capacity. So just how can you write winning capital jutification proposal? This article describes how you can make this happen.
The 12 Cardinal Sins of ERP Implementation
By: Richard G. Ligus CMC CPCM | 01/02/2009 | ManagementThe biggest single issue in ERP is the failure of a successful implementation. It is mind-boggling to continually encounter companies who make major ERP gaffes in this day and age, especially since most of the trials and tribulations of MRPII implementation were suffered and learned from in the early 1980's with alpha, beta and gamma releases. Industry statistics show that >60% of ERP implementation starts historically fail. Does this mean that you are doomed from the start?
Implementing Radical Change: The Right Stuff
By: Richard G. Ligus CMC CPCM | 07/03/2006 | ManagementSome companies are making substantial progress in becoming highly competitive. What is it that these companies have that makes the difference? The following characteristics seem to be consistent in companies who are able to radically transform themselves