Simon Buehring is a project manager, consultant and trainer. He works for KnowledgeTrain which offers PRINCE2 courses in the UK and overseas. Simon has extensive experience within the IT industry in the UK and Asia. He can be contacted via the KnowledgeTrain project management course website.
In my previous post (Why projects fail?) I explained the background to the C-NOMIS Information System project initiated by the National Offender Management Service (NOMS) in 2004.
In April 2009 the National Audit Office published a report that declared the failure of the original C-NOMIS and described how the project had demonstrated seven out of the eight primary causes of project failure. C-NOMIS has now been re-scoped and is earmarked for delivery in 2011. However, important questions remain regarding the way in which the project was managed, the length of time for which mis-management of the project was tolerated, and the value-for-money that can be expected from vast government programmes of this kind.
This article deals with the first of the OGC’s eight causes of project failure: the absence of any clear link between the project and the key strategic priorities of the parent organisation.
The “key strategic priority” of NOMS was to reduce the rate of re-offending in the UK, through the implementation of end-to-end offender case management. This would entail matching a single case manager for every offender and making offender information available to the appropriate individuals within both the prison and probation services.
The C-NOMIS project was set up to create a single, integrated database for all offender information. By integrating the information management systems across over 140 prisons and the 42 administrative areas of the National Probation Service, NOMS hoped to redefine how information about offenders is managed, in order to improve the continuity, consistency and efficacy of offender case management.
To this extent, C-NOMIS was clearly aligned to the strategic objectives of the organisation. However, the absence of any project-programme plan and failure to define the link between the project and the programme led to C-NOMIS being regarded as an independent IT project, rather than as a part of an IT-enabled business change programme.
As the government-standard PRINCE2 and MSP guidance makes clear, any project that is treated as independent of its programme or business context is in danger of being implemented for its own sake, regardless of whether it actually benefits the organisation’s strategy.
Furthermore, independence can also lead to insufficient external support to maximise the value of the project’s outputs. In the case of C-NOMIS, this was seen in the absence of any attempt to integrate the various information management systems currently in use. Even if C-NOMIS had delivered the expected IT solution, its benefits were automatically compromised by the difficulties imposed by the existing systems. As it was, the various systems complicated the design of the C-NOMIS database, encouraging the scope-creep that eventually led to the demise of the project.
Summary and solutions
Effective project-programme alignment is clearly crucial to project management success. But how do programme managers, business leaders and project managers make sure that their projects are strategically worthwhile and supported as such?
• There must be continued business justification via a detailed and thorough Business Case which must include a full appreciation of the expected benefits and costs involved
• The Business Case must be monitored at regular intervals throughout the lifecycle of the project (NB: this is one area covered in our PRINCE2 training courses)
• Portfolio management tools such as the Prioritisation Model can be used to evaluate the relative worth of individual projects and programmes
• An effective project management office should be established to ensure centralised support to projects and to provide a reliable source of information about an organisation’s project management activity (NB: learn more about creating a portfolio, programme and project management office through the P3O best practice model)
Looking ahead …
The ill-defined link between the C-NOMIS project and the key strategic priorities of the National Offender Management Service was one partial cause of the project’s failure. In my next post I am going to look at the next of the OGC-defined causes of project failure – the lack of clear senior management, ownership and leadership.
- Related Videos
- Related Articles
- Ask / Related Q&A
- Project Failure - What are the reasons for and statistics on it?
- Project Failures and Project Success
- The Main Reasons For Six Sigma Project Failures
- How to Dealing With Project Failure
- Avoiding project failure
- Software Project Failure Causes
- Project Issues Every Manager Should Prepare for
- Ten Tips for Running Successful Projects




How Can You Stay Passionate in Business?
By: Simon Johnnson | 29/11/2009When it comes to building yourself a new business empire, one of the key things that must walk hand in hand with you is passion. Passion is an intense desire, a conviction that sets in your heart as a rock to overpower all challenges, and to never sway from the...
How Can You Stay Motivated While Building a Business?
By: Simon Johnnson | 29/11/2009When you are about to start a business online, you need a little more than just talent and technical skill to stick through the challenges and become a success at the very end. What you need more than anything else is a rock hard motivation that will be constantly fuelled...
Hire a Headhunter OR do it yourself!
By: didier schmidt | 28/11/2009Now you can headhunt yourself or get headhunted. Just do it yourself and find the best for less!
Self Storage Solution Saves Inventories From Floods
By: A.Noton | 28/11/2009Whether it is for a business or a home, there is always a need for more space to store extra items and inventory. One way of storing items that has become popular in recent years is renting a self storage unit. Self storage units are a great place to store...
Myriad Inc. Offers Professional Usa It Project Management Training Services
By: Toan Dinh | 28/11/2009Myriad Inc. is an industry leading provider of USA IT project management training and business optimization, building on the success of every client with an expert staff and high-quality products.
AirTight Management for Strategic and Operational Excellence
By: cleveral | 28/11/2009Less than 1 in 100 companies will grow to even $5,000,000 in sales or more. When they do most founders will be replaced by ‘professional’ CEOs by investors or boards. Sometimes even by the choice of the founder who realizes he or she has outgrown their experience level.
Reasons to hire a marquee
By: Gen Federico | 28/11/2009There are many reasons to hire a marquee for a special event or occasion. Many people hire a marquee rather than an indoor venue such as a hotel as it is a very cost effective, flexible way to host a gathering giving you a wider choice of theme and location.
Starting a Business? Understanding Your Estimated Tax Payments
By: K. MacKillop | 27/11/2009If you organize your business as a single-owner LLC or elect to have your multi-owner LLC taxed as a partnership, you will have to pay estimated quarterly taxes to the IRS after your first year of business. If you are earning a substantial profit during your first year, you may...
Why Projects Fail? Part 4
By: projectmanuk | 24/11/2009 | ManagementThis article deals with the fourth of the OGC’s eight causes of project failure: poor approach to project and risk management.
Why Projects Fail? Part 3
By: projectmanuk | 20/11/2009 | ManagementThis article deals with the third of the OGC’s eight causes of project failure: insufficient or ineffective engagement with project stakeholders.
Why Projects Fail? Part 2
By: projectmanuk | 19/11/2009 | ManagementThis post deals with the second of the OGC’s eight causes of project failure: the lack of effective or clear senior management, ownership or leadership at higher levels within the organisation.
Why Projects Fail? Part 1
By: projectmanuk | 13/11/2009 | ManagementIn April 2009 the National Audit Office published a report that declared the failure of the original C-NOMIS and described how the project had demonstrated seven out of the eight primary causes of project failure. C-NOMIS has now been re-scoped and is earmarked for delivery in 2011. However, important questions remain regarding the way in which the project was managed, the length of time for which mis-management of the project was tolerated, and the value-for-money that can be expected from vast
ISEB Software Testing Systems Analysis Diploma
By: projectmanuk | 14/07/2009 | ManagementThe ISEB Foundation Certificate in Software Testing is the international standard training-course and qualification for software testers, developers and solution architects. It is also a key specialist module for the ISEB Systems Development Diploma, which is an important addition to the CV of any IT professional.
The Principles of Risk Management
By: projectmanuk | 02/07/2009 | ManagementEvery project manager and business leader needs to be aware of the practices and principles of effective risk management. Understanding how to identify and treat risks to an organisation, a programme or a project can save unnecessary difficulties later on, and will prepare managers and team members for any unavoidable incidences or issues.
Critical Path Software Training
By: projectmanuk | 26/06/2009 | ManagementCreating a realistic schedule is a key responsibility of any project manager. This schedule must be updated regularly throughout the duration of the project to ensure that the project manager is aware of any issues or delays that might affect the product delivery date. Too many delays can lead to additional expense, customer dissatisfaction and project failure.