Critical Path Mapping

Critical Path Mapping with Activity Network Diagrams

The activity network diagram is a method of displaying the timelines of all the various subtasks that are involved in any project. By doing this, the total task duration and the earliest and latest start and finish times for each task are also calculated and displayed. In addition to showing which subtasks are critical to on-time task completion, the activity network diagram can help determine where extra effort to speed a subtask will have the greatest payoff to overall speed.

The activity network diagram has had a relatively long history, dating back to the 1930s. In the 1950s, the technique emerged as the Program Evaluation Research Technique (PERT) and as the Critical Path Method (CPM). There are several ways to represent the output of the PERT/CPM process.

The method called the activity-on-arrow or, more simply, the arrow diagram will be reviewed in this article. An arrow diagram treats numbered nodes as instantaneous stop/start points for activities. The activities themselves are considered to take place on the arrows connecting the nodes.

What can it do for you?
An activity network diagram can show you which activities or which series of activities is critical to the timing of a more complex collection of interactive activities. This can be very helpful in deciding where and when to apply extra energy to keep projects on time. Creating an activity network diagram is time-consuming, however, so you should consider these questions before you decide to create one:

1. Is the task a complex one with simultaneous paths that must be coordinated? Creating a diagram for a relatively simple task may be a waste of time.

2. Are the durations of the subtasks known with relative certainty? If the actual timing of events is markedly different from diagram times, it will have little value, and people will dismiss the diagram as a useless exercise.

3. Are the task and the timing of the task completion critical to the organization? The effort involved in creating a diagram should be applied to tasks that have little margin for timing error and have either serious consequences if completion of the overall task is delayed or large rewards if completion can be speeded.

Critical path mapping can be especially valuable in project bounding and in the measure and improve phases of the Lean Six Sigma methodology.

How do you do it?
1. Assemble the right team. The team must have either personal knowledge of the timing of all the subtasks involved or connection to that information. The team should include managers and other employees as close to the actual situation as possible.
2. Identify all of the subtasks necessary to complete the overall task. You might use brainstorming techniques or begin with a list of tasks from a previous project. Record the tasks so that you can rearrange them. A good way to do this is to write each job on the top half of a 3x5 card or Post-It™ note. (The bottom half of the card will be used for timing data later in the process.)
3. Put the activity cards in the sequence in which they must be performed to complete the overall task. To do this, create paths or strings of tasks that follow one after the other. These strings will often describe sequences of activities that occur in parallel with each other. After all the activities are in some string or path of activities, create the overall sequence by connecting the paths. These connections will show where jobs or tasks require input from parallel sequences before the next task can begin. Feel free to add new cards for missing tasks or to remove duplicates.
4. Assign time duration to each task or job. Write it on the bottom half of the card. Since you will be adding these times, keep the numbers consistent. For instance, do not have some cards showing days for completion, some showing hours and some showing minutes. Select the Lowest Common Denominator.
5. Calculate the shortest possible time within which the overall task can be completed by adding the times of each subtask to find the path of the longest cumulative duration. This is the critical path. Knowing the critical path is important because this will tell if the time objectives of the project are attainable. The critical path identifies those jobs or tasks that have no slack. Each must be done on time if the project is to stay on schedule. The critical path also identifies targets for improvement to increase speed. (If tasks on the critical path can be speeded, the overall time to complete the project may be able to be shortened. Remember, however, that if a task on the critical path is speeded up, a different path may become the critical path.)
6. Calculate the earliest starting and finishing times and the latest starting and finishing times for each job or subtask in the project. Begin at the start of the diagram. The earliest start time for each job is the cumulative duration of all the previous jobs on that path. The earliest finish time is the earliest start time plus the duration of that task. Repeat this process for each job on each path until you reach the finish point. Next calculate the latest start and finish times. Begin with the earliest finish time at the end of the diagram.

To calculate the slack time for any job or task, subtract the earliest start time from the latest start time. All of the jobs on the critical path, by definition, will have zero slack time. Remember that slack time is dependent on the time of completion of the previous job or task. If some of the slack time in a path other than the critical path is used in an early task, the slack times for the remaining tasks in that path will each be reduced by that amount.)
Note: A dummy is an extra node symbol used to clarify an activity network diagram if one node has more than one job or task feeding into it from one other node. Since the diagram cannot show two activities coming from one node and going to another, a dummy node is created, with zero as the job duration shown on the arrow connecting them.
7. Review the completed activity network diagram with the people who will be doing the work described by it. Consider any feedback. Expand or modify the diagram as necessary to fit the actual situation.

Now what?
As a tool, the activity network diagram is like a time-map of any time-sensitive project. As you are proceeding down the paths of the project, the map will help keep you on track. If you should falter or wander off the path, the map can be used to help get you back on the critical path. This description of the activity network diagram will help you to manually calculate and construct a process map.
Automated tools, such as SigmaFlow, are also available. SigmaFlow produces other valuable scheduling information, as well. Computer scheduling programs like SigmaFlow are able to easily deal with complex processes, recalculating times whenever you modify the data.

A critical path map can help uncover opportunities for increasing speed. Used in this fashion, critical path mapping is another tool to make the Lean Six Sigma method work smoothly. It is important to remember, however, that these diagrams, whether produced manually or by computer, are not intended to drive you, but to signal you if something is wrong.

Steven Bonacorsi

Steven Bonacorsi is a Senior Master Black Belt instructor and coach. Steven Bonacorsi has trained hundreds of Master Black Belts, Black Belts, Green Belts, and Project Sponsors and Executive Leaders in Lean Six Sigma DMAIC and Design for Lean Six Sigma process improvement methodologies.
The AIT Group, Inc.
Steven Bonacorsi, Solution Provider
Lean Six Sigma Master Black Belt
3135 South Price Road, Suite 115
Chandler, AZ 85248-3549
Phone: +(1) 888.826.2484
E-mail: americas@theaitgroup.com http://www.theaitgroup.com

Rate this Article: 5 / 5 stars - 1 vote(s)
Print Email Re-Publish

Add new Comment



Captcha

  • Latest Project Management Articles
  • More from Steven Bonacorsi

Sustainable Building - Advice For Small Development Proposals Has Become More Affordable

By: Paul Giesberg | 13/11/2009
In the UK the requirements to build sustainable homes become more and more onerous. The trouble is that most of the requirements have been written with large development projects in mind. It is now a few years since the first of these requirements were imposed on all new development proposals and the sector, both planning officers and consultants, has now learned how to address the sustainability requirements of small development proposals effectively.

Environmental Statements - Addressing Contaminated Land Issues

By: Paul Giesberg | 13/11/2009
Contaminated land is often managed in the same ways as the various environmental receptor groups, although it is principally a cause of impacts rather than a receptor.Sticking to the structured approach of an environmental statement is essential to ensure a clear description of the existing environmental condition, the potential impacts and the actions taken to avoid, minimise, offset or manage the impacts.

The Implication of the UK Renewable Energy Strategy For Development Projects

By: Paul Giesberg | 13/11/2009
The department for Energy and Climate Change has recently published the UK Renewable Energy Strategy. This article examines the implications for development projects in the UK.

Find a Responsible Electrical Contractor to Avoid Counterfeit Electrical Products

By: Business Local Listings | 12/11/2009
Manufacturers of original electrical products can be negatively affected by the existence of counterfeit electrical products in the market. When their products are counterfeited, their reputations are damaged and the customer trust that they had painstakingly built over the years is put at risk. Sales of the counterfeit electrical products also represent loss of sales in their original electrical products. Counterfeiting is, therefore, comparable to theft of the products of original manufacturer

Selecting the Right Material for Above Ground and Ground Level Pool Decks

By: Business Local Listings | 11/11/2009
An outdoor living space is never complete without a pool. It does not even have to be a big pool. A good designer should be able to make even a mini pool look stylish with the right choice of materials for the deck and the rest of the outdoor space area.

Why You Need Professional Electrical Contractors and Electricians

By: Business Local Listings | 11/11/2009
Electricity can be very dangerous and should never be tampered with by non-professionals. Neither should you place your trust and safety in the hands of informal service providers who claim to have the necessary skills and offer their services at much lower costs. Remember that you need a licensed electrical contractor company with professionally certified electricians for the design, installation and maintenance of electrical systems for your residential, commercial and industrial sites.

Choosing the Right Materials for Patios, Driveways, and Pool Decks

By: Business Local Listings | 11/11/2009
Paver materials come in concrete, brick, sandstone, and many more. To date, it is one of the most versatile material being used for making driveways, patios, and pool decks. Choosing the right material for your outdoor living space should be thought of carefully because it will be the first thing you see before entering the house. It also serves as your family's alternative activity and receiving area for friends and guests.

Digital Photography Guide To Professionals Trickery

By: Dan Feildman | 10/11/2009
Amazing Guide To Digital Photography complete with a FREE REPORT, PLUS A FREE CD will be sent to your own very home... The Complete Digital Photography Guide Offer will soon expire...

5s - Foundation for Continuous Improvement

By: Steven Bonacorsi | 09/02/2009 | Management
5s is a continuous improvement methodology that is simple to understand and easy to implement and considered a foundation for continuous improvement. Sort, Set in Order, Shine, Standardize, and Sustain

Mistake Proofing

By: Steven Bonacorsi | 02/10/2008 | Management
Mistake proofing is a technique for eliminating errors. It is based upon the premise that it is good to do something right the first time; it is even better to make it impossible to do it wrong the first time. The idea is to make it impossible to make a mistake. You may also hear the term, Poka-Yoke or Error Proofing applied to mistake proofing.

Cause and Effect Diagrams (fishbone Diagrams)

By: Steven Bonacorsi | 25/04/2008 | Management
The first such cause-and-effect diagram was used by Kaoru Ishikawa in 1943 to explain to a group of engineers at the Kawasaki Steel Works how various work factors could be sorted and related. In recognition of this, these diagrams sometimes are called Ishikawa diagrams. They are also called fishbone diagrams, because they look something like fish skeletons.

Critical Path Mapping

By: Steven Bonacorsi | 24/04/2008 | Project Management
The activity network diagram has had a relatively long history, dating back to the 1930s. In the 1950s, the technique emerged as the Program Evaluation Research Technique (PERT) and as the Critical Path Method (CPM). There are several ways to represent the output of the PERT/CPM process.

Box Plots

By: Steven Bonacorsi | 21/04/2008 | Management
Box-and-whisker diagrams, or Box Plots, use the concept of breaking a data set into fourths, or quartiles, to create a display. The box part of the diagram is based on the middle (the second and third quartiles) of the data set. The whiskers are lines that extend from either side of the box. The maximum length of the whiskers is calculated based on the length of the box. The actual length of each whisker is determined after considering the data points in the first and the fourth quartiles.

Dot Plots

By: Steven Bonacorsi | 20/03/2008 | Management
A dot plot graphically records variable data in such a way that it forms a picture of the combined effect of the random variation inherent in a process and the influence of any special causes acting on it. To understand the power of dot plots as a basic tool, it first helps to visualize how variation occurs.

Run Charts

By: Steven Bonacorsi | 13/03/2008 | Project Management
Run charts can be very valuable in helping your search for sources of variation. They are easy to plot and easy to interpret. The sampling is uncomplicated, and there are no statistical computations to make. They can also be applied to almost any process or any data.

Scatter Diagrams

By: Steven Bonacorsi | 10/03/2008 | Training
A scatter diagram shows the correlation between two variables in a process. These variables could be a Critical-To-Quality (CTQ) characteristic and a factor affecting it, two factors affecting a CTQ or two related quality characteristics. Dots representing data points are scattered on the diagram. The extent to which the dots cluster together in a line across the diagram shows the strength with which the two factors are related.

Submit Your Articles Free: Signup
Article Categories




Use of this web site constitutes acceptance of the Terms Of Use and Privacy Policy | User published content is licensed under a Creative Commons License.
Copyright © 2005-2008 Free Articles by ArticlesBase.com, All rights reserved. (0.22, 6, w1)