Project management plan

As soon as the project manager has received his brief or project instructions, he must produce a document which distils what is generally a vast amount of information into a concise, informative and well-organized form that can be distributed to all members of the project team and indeed all the stakeholders in the project. This document is called a project management plan (PMP), but is also sometimes just called a project plan, or in some organizations a coordination procedure.

The PMP is one of the key documents required by the project manager and his/her team. It lists the phases and encapsulates all the main parameters, standards and requirements of the project in terms of time, cost and quality/performance by setting out the ‘Why’, ‘What’, ‘When’, ‘Who’, ‘Where’ and ‘How’ of the project. In some organizations the PMP also includes the ‘How much’, that is the cost of the project. There may, however, be good commercial reasons for restricting this information to key members of the project team.

The contents of a PMP vary depending on the type of project. While it can run to several volumes for a large petrochemical project, it need not be more than a slim binder for a small, unsophisticated project.

There are, however, a number of areas and aspects which should always feature in such a document. With the permission of the British Standards Institution, the main headings of what is termed the Model Project Plan are given below, but augmented and rearranged in the sections given above.

General

  1. Foreword
  2. Contents, distribution and amendment record
  3. Introduction
    1. Project diary
    2. Project history

The Why

  1. Project aims and objectives
    1. Business case

The What

  1. General description
    1. Scope
    2. Project requirement
    3. Project security and privacy
    4. Project management philosophy
    5. Management reporting system

The When

  1. Programme management
    1. Programme method
    2. Program software
    3. Project life cycle
    4. Key dates
    5. Milestones and milestone slip chart
    6. Bar chart and network if available

The Who

  1. Project organization
  2. Project resource management
  3. Project team organization
    1. Project staff directory
    2. Organizational chart
    3. Terms of reference (TOR)
      1. for staff
      2. for the project manager
      3. for the committees and working group

The Where

  1. Delivery requirements
    1. Site requirements and conditions
    2. Shipping requirements
    3. Major restrictions

The How

  1. Project approvals required and authorization limits
  2. Project harmonization
  3. Project implementation strategy
    1. Implementation plans
    2. System integration
    3. Completed project work
    4. Acceptance procedure
    5. Procurement strategy
      1. Cultural and environmental restraints
      2. Political restraints
      3. Contract management
      4. Communications management
      5. Configuration management
        1. Configuration control requirements
        2. Configuration management system
        3. Financial management
        4. Risk management
          1. Major perceived risks
          2. Technical management
          3. Tests and evaluations
            1. Warranties and guarantees
            2. Reliability management (see also BS 5760: Part 1)
              1. Availability, reliability and maintainability (ARM)
              2. Quality management
              3. Health and safety management
              4. Environmental issues
              5. Integrated logistic support (ILS) management
              6. Close-out procedure

The numbering of the main headings should be standardized for all projects in the organization. In this way the reader will quickly learn to associate a clause number with a subject. This will not only enable him/her to find the required information quickly, but will also help the project manager when he/she has to write the PMP. The numbering system will in effect serve as a convenient checklist. If a particular item or heading is not required, it is best simply to enter ‘not applicable’ (or NA), leaving the standardized numbering system intact.

Apart from giving all the essential information about the project between two covers, for quick reference, the PMP serves another very useful function. In many organizations the scope, technical and contractual terms of the project are agreed in the initial stages by the proposals or sales department. It is only when the project becomes a reality that the project manager is appointed. By having to assimilate all these data and write such a PMP (usually within two weeks of the hand-over meeting), the project manager will inevitably obtain a thorough understanding of the project requirements as he/she digests the often voluminous documentation agreed with the client or sponsor.

Clearly not every project requires the exact breakdown given in this list and each organization can augment or expand this list to suit the project. If there are any subsequent changes, it is essential that the PMP is amended as soon as changes become apparent so that every member of the project team is immediately aware of the latest revision. These changes must be numbered on the amendment record at the front of the PMP and annotated on the relevant page and clause with the same amendment number or letter.

The contents of the project management plan are neatly summarized in the first verse of the little poem from the Elephant’s Child by Rudyard Kipling:

  • I keep six honest serving-men
  • (They taught me all I knew);
  • Their names are What and Why and When,
  • And How and Where and Who.
Hassan Eliwah

If you wish to find projects management solutions and services Visit: projequip: projects management solutions, where you can find HQ project management articles and news

Rate this Article: 0 / 5 stars - 0 vote(s)
Print Email Re-Publish

Add new Comment



Captcha

  • Latest Project Management Articles
  • More from Hassan Eliwah

The Code for Sustainable Homes and Renewable Energy

By: Paul Giesberg | 24/11/2009
It appears therefore a relatively straightforward excercise to detemine what would be the most appropriate system or mix of sustems to include in any particular development. There are however a number of issues that need to be considered that make the process less straightforward. This article explains these issues in more detail.

Code for Sustainable Homes: scoring well in the energy section

By: Paul Giesberg | 24/11/2009
The Code for Sustainable Homes is a sustainability assessment tool for new built housing. It considers a number of topics in nine different categories. Of these categories the one on energy use can be considered as the most important category: it accounts for more than 35% of the total score. Scoring well in the energy section is therefore essential to gain a good Code for Sustainable Homes rating.In this article I review the credit requirements and discuss how feasible it is to meet each these.

Code for Sustainable Homes: scoring well in the energy section

By: Paul Giesberg | 24/11/2009
The Code for Sustainable Homes is a sustainability assessment tool for new built housing. It considers a number of topics in nine different categories. Of these categories the one on energy use can be considered as the most important category: it accounts for more than 35% of the total score. Scoring well in the energy section is therefore essential to gain a good Code for Sustainable Homes rating.In this article I review the credit requirements and discuss how feasible it is to meet each these.

Code for Sustainable Homes: scoring well in the energy section

By: Paul Giesberg | 24/11/2009
The Code for Sustainable Homes is a sustainability assessment tool for new built housing. It considers a number of topics in nine different categories. Of these categories the one on energy use can be considered as the most important category: it accounts for more than 35% of the total score. Scoring well in the energy section is therefore essential to gain a good Code for Sustainable Homes rating.In this article I review the credit requirements and discuss how feasible it is to meet each these.

Calculating the hours of experience for the PMP application - Part 3

By: Bogdan Gorka | 23/11/2009
I have developed a model in MS Excel to calculate the hours needed for the PMP exam application.

Calculating the hours of experience for the PMP application - Part 2

By: Bogdan Gorka | 23/11/2009
I remember quite well that calculating the hours of experience for the PMP Exam application was difficult for me because I had no clue how to approach it. I took me weeks to find ideas on the internet that allowed me some progress. As probably most people who are not consultants, I was not obliged to maintain my weekly timesheets. I had to find some other way.

Calculating the hours of experience for the PMP application - Part 1

By: Bogdan Gorka | 23/11/2009
In order to be eligible to sit for the PMP exam, you also need to calculate the hours of your experience. These calculations will be needed for your application process. In this article I am showing you how to do it properly

PROJECT MANAGEMENT AND ITS IMPORTANT STEPS:

By: M Mohsin Khan | 22/11/2009
Project management is the discipline of planning, organizing, and managing resources to bring about the successful completion of specific project goals and objectives. It is often closely related to and sometimes conflated with program management.

How to handle error messages

By: Hassan Eliwah | 18/10/2009 | Operating Systems
When we were kids, we imagined that the future held flying cars and moon bases. Technology and humanity would be in perfect sync. Our machines would anticipate our needs, leaving us to pursue only the most relevant, important work.

Why MAC address filtering is not perfect

By: Hassan Eliwah | 18/10/2009 | Operating Systems
MAC addresses - which are different for each device on your network - may seem to be the perfect way to keep out intruders, but there’s a catch. Since you can change the MAC address on most modern hardware, someone could theoretically connect to a filtered network by spoofing the MAC address.

Disposable Jewelry

By: Hassan Eliwah | 18/10/2009 | Jewelry
Ask yourself a question, “Why do people buy jewelry?” Personal adornment? Possibly beauty? Certainly investment? These may be reasons for some, but the number one reason for the purchase of jewelry is status. Pure and simple. If I can have something you can’t have I’m better than you.

How to tell a real diamond from a fake

By: Hassan Eliwah | 18/10/2009 | Jewelry
People want to know if there is some simple test they can do at home or little tricks of the trade to tell if the ring they own is a valuable heirloom or of the Cracker Jack variety. Without question the quickest and most reliable method for authenticity would be an independent appraisal. This can be accomplished easily enough by looking under “Appraisal (Jewelry)” in your yellow pages.

About OpenGL

By: Hassan Eliwah | 18/10/2009 | Computer Games
OpenGL is a procedural rather than descriptive interface. In order to generate a rendering of a red sphere the programmer must specify the appropriate sequence of commands to set up the camera view and modeling transformations, draw the geometry for a sphere with a red color. etc.

The Self-Affirming Culture of Gaming

By: Hassan Eliwah | 18/10/2009 | Computer Games
In these three examples, we have seen that economic, political, and legal activity that crosses the membrane between synthetic worlds and the Earth serves mostly to blur any distinction between what is synthetic and what is Earthly. This argument may be applied more generally to the world of gaming as a whole.

General introduction to Risk management

By: Hassan Eliwah | 18/10/2009 | Project Management
Every day we take risks. If we cross the street we risk being run over. If we go down the stairs, we risk missing a step and tumbling down. Taking risks is such a common occurrence, that we tend to ignore it. Indeed, life would be unbearable if we constantly worried whether we should or should not carry out a certain task or take an action, because the risk is, or is not, acceptable.

Project management plan

By: Hassan Eliwah | 18/10/2009 | Project Management
As soon as the project manager has received his brief or project instructions, he must produce a document which distils what is generally a vast amount of information into a concise, informative and well-organized form that can be distributed to all members of the project team and indeed all the stakeholders in the project.

Submit Your Articles Free: Signup
Article Categories




Use of this web site constitutes acceptance of the Terms Of Use and Privacy Policy | User published content is licensed under a Creative Commons License.
Copyright © 2005-2008 Free Articles by ArticlesBase.com, All rights reserved. (0.39, 0, w1)